Bridge construction means road closures

HOUSTON Additional bridge segments will be delivered and installed during this time. Alternative routes are Shepherd or Waugh.

Here's the closure schedule:
Saturday, October 23, 2010: 12 a.m. to 12 p.m. - Northbound lanes of the Studemont Bridge from Allen Parkway to Memorial Court
Sunday, October 24, 2010: No closure listed
Monday, October 25, 2010: 12 a.m. to 4 p.m. - Montrose / Studemont exit off Allen Parkway westbound
Tuesday, October 26, 2010: 10 a.m. to 3 p.m. - Montrose / Studemont exit off Allen Parkway westbound
Wednesday, October 27, 2010: 10 a.m. to 3 p.m. - Montrose / Studemont exit off Allen Parkway westbound
Thursday, October 28, 2010: No closure planned at this time
Friday, October 29, 2010: 12 a.m. to 4 p.m. - Montrose / Studemont exit off Allen Parkway westbound

Groundbreaking for the Rosemont Bridge was on March 13, 2010, and expected completion date is in January 2011.

For more information on the Houston Parks and Recreation Department, call (832) 395-7022 or visit www.houstonparks.org.

Check real-time traffic information in our ABC13.com traffic section