This long-term total closure was originally scheduled to begin March 8 and last for eight weeks. In an effort to minimize traffic impacts in the area, TxDOT worked with contractors and developed a four week construction schedule that could begin after the Spring Break vacation. This long-term closure is needed to allow the contractor space to install new storm sewer drains and reconstruct the roadway in the area.
Detour information is listed below:
- Northbound Bingle/Voss traffic will detour left on Las Alamedas Way, turn right at the stop sign onto the I-10 eastbound frontage road and turn left onto Bingle northbound.
- Southbound Bingle/Voss traffic will detour to the I-10 westbound frontage road to U-turn at the signalized intersection at Campbell to the I-10 eastbound frontage road, turn right on Las Alamedas Way and merge onto Voss Rd.