New data from the city's public works department dated November 10th said there is still a daily average of around 300 leaks per day in water infrastructure.
It was over 500 a day during the summer, but the average was less than 100 a day late in the spring.
[Ads /]
It's also still taking two to five weeks to fix minor leaks, much to the chagrin of people ABC13 spoke with Tuesday morning who work near one at Almeda Genoa and Radio Road in southeast Houston.
"I just came to work, and it was just bubbling and looking like a stream of water," David Rice said. "That's a lot of good, clean water to be broken like that."
RELATED: Residents near Memorial Park cope with growing water leak for 2 months: 'It's getting a lot bigger'
Cooler temperatures haven't slowed Houston water leaks
The leak has been active since early November, so it's still below the city's current repair window.
[Ads /]
City officials have previously told us they strive to have leaks repaired in eight days or less.
A spokesperson from the public works department told ABC13 that the one we visited Tuesday along Almeda Genoa should be repaired by Friday.
Overall, the data from the department said approximately 6,550 leaks have been fixed by city crews and outside contractors since June 1.
Editorial Note: A previous version of this story said the city was still averaging 500 leaks a day.
For news updates, follow Chaz Miller on Facebook, Twitter and Instagram.
SEE ALSO: Nearly 20K calls for Houston water leaks logged as city increases repair funding in 2023 to $81M
$48M OK'd to repair Houston water leaks, bringing 2023 total to $81M